We wanted to give everyone a heads up for a large project that is on the horizon. All the main shut off valves, in every unit, is due to be changed by Trotter & Morton. We will be doing this in batches of 10 units per water shut down. Each shut down will affect half of the building; Floors 1-7 and Floors 8-15. There are 124 units remaining which means we will have at least 13 water shut downs over the next few months. Each unit will be further notified with the dates for access requirements.
This will require suite access over several days to accommodate the contractors in the following steps:
1. Simcon Construction- drywall and access panel removal. 1 day.
2. Trotter & Morton- plumbing work (removing old shut off valves and installing new ones). 1 day.
3. Simcon Construction- drywall repairs and access panel installation. Up to 5 days.
If you have any questions or concerns, please feel free to contact the on-site office at lbtoff1@telus.net or 403-263-1505.
Thank you for your understanding.
Sincerely,
Liberté Management Team
On behalf of the Board of Directors